The (73) process differs from the (74) process in that the former is primarily concerned with acceptance of the deliverables, while the latter is primarily concerned with correctness of the deliverables.
 
  A.  Perform Quality Assurance
 
  B.  Validate Scope
 
  C.  Control Quality
 
  D.  Define Scope




 
 
相关试题     专业英语 

  第73题    2008年下半年  
The Estimate Activity Resource process is closely coordinated with the (73)process.

  第74题    2021年上半年  
The key benefit of the Project( )is that it determines whether to scquire goods and services from outside the project,if so,what to acquire as weII ..

  第75题    2019年下半年  
Risk( )acknowledge the existence of a threat,but no proactive action is taken 。