Earned value management(EVM) integrates the scope baseline with the ( ) baseline, along with schedule baseline,to form the performance baseline, which helps the project management team assess and measure project performance and progress.
 
  A.  qulity
 
  B.  risk
 
  C.  change
 
  D.  cost




 
 
相关试题     专业英语 

  第71题    2019年下半年  
( )seeks to perform root cause investigation as to what is leading identified trends.

  第73题    2015年上半年  
Before a project schedule can be created,the schedule maker should have a(),an effort estimate for each task,and a resource list with availability f..

  第75题    2025年上半年  
Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. Th..