全部科目 > 信息系统项目管理师 >
2019年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.
 
  A.  project scope statement
 
  B.  work package
 
  C.  WBS
 
  D.  project scope plan




 
 
相关试题     专业英语 

  第72题    2019年上半年  
( ) is an open, distributed ledger that can record transations between two parties efficiently and in a verifiable and permanent way.

  第75题    2008年上半年  
Durin the project, requirements chan e for a variety of reasons. As needs chan e and as work proceeds, additional requirements are derived and chan es..

  第74题    2018年下半年  
The (73) process differs from the (74) process in that the former is primarily concerned with acceptance of the deliverables, while the latter is prim..