The intention of the(75)is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.
 
  A.  project work breakdown
 
  B.  project security authentication
 
  C.  project management
 
  D.  project flowchart




 
 
相关试题     专业英语 

  第75题    2020年下半年  
()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to t..

  第73题    2016年下半年  
Quality management ensures that an organization,product or service is (73)。It has four main components:quality planning,quality assurance,quality c..

  第73题    2009年上半年  
Many of the activities performed during the preliminary investigation are still being conducted in(71), but in much greater depth than before. Durin..