The strategies for handling risk comprise of two main types:negative risks, and positive risks. The goal of the plan is to minimize threats and maximize opportunities.When dealing with negative risks,there are three main response strategies (72),Transfer ,Mitigate .
 
  A.  Challenge
 
  B.  Exploit
 
  C.  Avoid
 
  D.  Enhance




 
 
相关试题     专业英语 

  第75题    2018年上半年  
():The process of translating the quality mangement plan into executable quality activities that incorporate the organization's quality policies in..

  第73题    2010年下半年  
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

  第75题    2010年下半年  
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.