2019年下半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
Risk( )acknowledge the existence of a threat,but no proactive action is taken 。
 
  A.  avoidance
 
  B.  transfer
 
  C.  mitigate
 
  D.  acceptance




 
 
相关试题     专业英语 

  第74题    2015年上半年  
Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling..

  第74题    2011年下半年  
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are..

  第72题    2009年上半年  
Many of the activities performed during the preliminary investigation are still being conducted in(71), but in much greater depth than before. Durin..