2010年下半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).
 
  A.  executive IT manager
 
  B.  project manger
 
  C.  change control board
 
  D.  project sponsor




 
 