2010年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.(74) is not a project configuration management tool.
 
  A.  Rational Clearcase
 
  B.  Quality Function Deployment
 
  C.  Visual SourceSafe
 
  D.  Concurrent Versions System




 
 