Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria.(74)is not a project selection method.
 
  A.  Benefit contribution
 
  B.  Expert judgment
 
  C.  Scoring models
 
  D.  Flow charting




 
 