Validate Scope is the process of formalizing acceptance of the completed ( ).
 
  A.  project deliverables
 
  B.  WBS
 
  C.  activities
 
  D.  milestones




 
 
相关试题     专业英语 

  第73题    2014年上半年  
Requirements management is the process of (73),analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communi..

  第74题    2012年上半年  
Your project is behind schedule due to conflict between team members .Haring resolved the conflict, to get the project back on schedule,you should co..

  第74题    2019年上半年  
Earned value management(EVM) integrates the scope baseline with the ( ) baseline, along with schedule baseline,to form the performance baseline, which..