2010年下半年 上午试卷 综合知识
第 75 题
关键词 WBS  
章/节 专业英语  
 
 
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.
 
  A.  independent resource
 
  B.  individual work load
 
  C.  work milestone
 
  D.  work package




 
 