In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. (73)are not output of activity definition.
 
  A.  Activity lists
 
  B.  Work Breakdown Structures
 
  C.  Activity Attributes
 
  D.  Milestone Lists




 
 