全部科目 > 系统集成项目管理工程师 >
2011年上半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
(73) are the four major activities of software configuration management.
① configuration identification ② statement report ③ change control
④ preparation of requirement document ⑤ configuration auditing
 
  A.  ①②③④
 
  B.  ①②④⑤
 
  C.  ①②③⑤
 
  D.  ②③④⑤




 
 
相关试题     专业英语 

  第75题    2018年下半年  
In a project plan, when the project manager schedules activities, he (or she) often uses ( ) method,This method, precedence relationships between acti..

  第73题    2010年上半年  
(73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

  第74题    2015年下半年  
Establishing a project (74) involves listing milestones,activities,and deliverables with intended start and finish dates,of which the scheduling of em..