2010年上半年 上午试卷 综合知识
第 71 题
章/节 专业英语  
 
 
Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.  
 
  A.  risk
 
  B.  problem
 
  C.  result
 
  D.  data




 
 