2009年上半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in  the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.
 
  A.  phases
 
  B.  processes
 
  C.  segments
 
  D.  picces




 
 