全部科目 > 系统集成项目管理工程师 >
2009年上半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in  the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.
 
  A.  plan
 
  B.  fraction
 
  C.  main
 
  D.  framework




 
 
相关试题     专业英语 

  第74题    2010年下半年  
Perform Quality Control is the process of monitoring and recording results ofexecuting the Quality Plan activities to assess performance and recommend..

  第75题    2016年下半年  
Human resource management is the management of human resources.It is a function in organizations designed to maximize employee(75)in sercice of an e..

  第72题    2021年下半年  
The organization shall undertake root causeanalysis and determine potential actions to preventthe occurrence or recurrence of().




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2026 All Rights Reserved