第 74 题
章/节 专业英语  
 
 
In project management and systems engineering, ( )is a deliverable-oriented breakdown of a project into smaller components. It is a key project deliverable that organizes the team's work into manageable sections.
 
  A.  RBS
 
  B.  PBS
 
  C.  GBS
 
  D.  WBS




 
 