全部科目 > 系统集成项目管理工程师 >
2012年上半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
Project manager believes that modifying the project scop may provide added valuefor the customer.The project manager should(73).
 
  A.  change the scope baseline
 
  B.  contact the customer to determine if the change adds value
 
  C.  call a meeting of the change control board
 
  D.  change the project's objectives




 
 
相关试题     专业英语 

  第71题    2020年下半年  
The main direction of Integration of Industrialization and Informatization is ( )。

  第71题    2013年下半年  
A (71) is a software that provides a method of communication between two electronic devices over the World Wide Web.

  第72题    2017年上半年  
( ) refers to the application of the Internet and other information techno1ogy in conventiona1 industries. It is an incomplete equation where various ..




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2026 All Rights Reserved
软考在线版权所有