Project manager believes that modifying the project scop may provide added valuefor the customer.The project manager should(73).
 
  A.  change the scope baseline
 
  B.  contact the customer to determine if the change adds value
 
  C.  call a meeting of the change control board
 
  D.  change the project's objectives




 
 
相关试题     专业英语 

  第75题    2019年上半年  
( )is a process of monitoring the status of the project to update the project costs and manage changes to the cost baseline。

  第75题    2017年上半年  
The key benefit of( )is that it provides guidance and direction on how the project costs will be managed throughout the project.

  第74题    2015年上半年  
(74) is the output of the quality planning.