Managing risk and documenting them is veryimportant inproject planning process. You are in the process of defining keyrisks, including constraints and assumptions, and plannedresponses and contingencies. These details will be included in the(73) .
 
  A.  project management plan
 
  B.  project baseline
 
  C.  riskresponse plan
 
  D.  risk baseline




 
 
相关试题     专业英语 

  第73题    2018年下半年  
Configuration management is focused on the specification of both the deliverables and the processes;While ( ) is focused on identifying, documenting,..

  第72题    2019年上半年  
( ) is the extension of internet connectivity into physical devices and everyday objects. Embedded with electronics, internet connectivity, and othe..

  第73题    2016年上半年  
In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the proje..