2013年上半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
The work that needs to be accomplished to deliver a product, service, or result with the specified features and functions is called ( 73 ).
 
  A.  scope management
 
  B.  integrated management
 
  C.  SOW
 
  D.  PMO




 
 