全部科目 > 系统集成项目管理工程师 >
2022年下半年 上午试卷 综合知识
第 72 题
章/节 专业英语  
 
 
In () ,the project scope, time,and cost are determined in the early phases of the life cycle.Any changes to the scope are carefully managed.
 
  A.  predictive life cycle
 
  B.  iterative life cycle
 
  C.  incremental life cycle
 
  D.  adaptive life cycle




 
 
相关试题     专业英语 

  第71题    2019年下半年  
( )contributes to monitoring and data collection by defining security monitoring and date collection requirements.

  第73题    2017年上半年  
For any information system to serve its purpose ,the information must be( )when it ìs needed.

  第73题    2022年上半年  
The project () processes include: develop project charter, develop project management plan,direct and manage project work,manage project knowledg..




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2025 All Rights Reserved