The project budget has been finalized.Additional work has been discovered that was not planned forin the budget or project scope. (74) could provide the fund to cover the newly discovered work item.
 
  A.  Contingency reserve
 
  B.  Project profit
 
  C.  Managementreserve
 
  D.  Special fund




 
 
相关试题     专业英语 

  第75题    2009年下半年  
The Development of Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans ..

  第74题    2013年下半年  
(74) can be considered as part of risk mitigation.

  第75题    2018年上半年  
( )is the sum of all budgets established for the work to be performed.