2012年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
The project budget has been finalized.Additional work has been discovered that was not planned forin the budget or project scope. (74) could provide the fund to cover the newly discovered work item.
 
  A.  Contingency reserve
 
  B.  Project profit
 
  C.  Managementreserve
 
  D.  Special fund




 
 