2013年下半年 上午试卷 综合知识
第 73 题
关键词 PERT  
章/节 专业英语  
 
 
(73) is not the advantage of GERT(graphical evaluation and review techniques) as compared with PERT(project evaluation and review techniques).
 
  A.  Allowing looping
 
  B.  Allowing for dummy tasks
 
  C.  Allowing branching
 
  D.  Allowing multiple project end results




 
 