2024年下半年 上午试卷 综合知识
第 72 题
章/节 专业英语  
 
 
In () ,the project scope, time,and cost are determined in the early phases of the life cycle.Any changes to the scope are carefully managed.
 
  A.  iterative life cycle
 
  B.  adaptive life cycle
 
  C.  incremental life cycle
 
  D.  predictive life cycle




 
 