2014年上半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
”Cost of quality ”is a project management concept that includes cost of ( ).
 
  A.  exceedings requirements
 
  B.  Changed to the requirements
 
  C.  Ensuring conformance to requirements
 
  D.  The quality control requirements




 
 