第 74 题
章/节 专业英语  
 
 
During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate. This duration is what you commit to complete the project. What is wrong with the scenario? ( ) .
 
  A.  The team did not create the estimate and estimating tales too long using that method
 
  B.  The team did not create the estimate and a network diagram was not used
 
  C.  The estimate is too long and should be created by management
 
  D.  The project estimate;should be the same as the customer's required completion date




 
 
相关试题     专业英语 

  第72题    2012年下半年  
Supervision will manage the implementation and the configuration of the different types of project documents, not including (72).

  第74题    2010年下半年  
Changes often happen in (74).

  第75题    2017年下半年  
( )seeks to build confidence that a future output or an unfinished output ,also known as work in progress,will be completed in a manner that meets t..




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2025 All Rights Reserved
软考在线版权所有