A formally chartered group responsible for reviewing,evaluating,
approving,delayingor rejecting changes to the project,and for recording and communication such decisions. It is the ().
 
  A.  Change Control System
 
  B.  Change Control Board
 
  C.  Change Control Tool
 
  D.  Change Management Plan




 
 