2016年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
A critical path for a project is the series of activities that determine(74) by which the project can be completed.
 
  A.  the earliest time
 
  B.  the latest time
 
  C.  the total time
 
  D.  the free time




 
 