The project management plan defines how the project is executed,monitored and controlled , and closed . it is progressively elaborated by updates , and controlled and approved through the Perform Integrated( )process.
 
  A.  Cost control
 
  B.  Schedule Control
 
  C.  Change Control
 
  D.  Risk Control




 
 