Schedule control is concerned with all the followings except (74) .
 
  A.  changing the schedule based on customer demands
 
  B.  determining that the schedule has changed
 
  C.  influencing the factors that create schedule changes to ensure that the changes are beneficial
 
  D.  managing the actual changes when and as they occur




 
 