( )describes the configurable items of the project and identifies items that will be recorded and updated so that the product of the project remains consistent and operable.
 
  A.  The configuration management plan
 
  B.  The change management plan
 
  C.  The requirements traceability matrix
 
  D.  The change baseline




 
 
相关试题     专业英语 

  第74题    2023年下半年  
( )must be between on-line deployment and final acceptance.

  第73题    2019年上半年  
The perform Integrated Change Contorl process is the ultimate responsibility of the (73).Although changes may be initiated verbally,they should be r..

  第73题    2010年上半年  
(73) is one of the techniques used for estimating activity durations.