免费智能真题库 > 历年试卷 > 信息系统项目管理师 > 2025年上半年 信息系统项目管理师 上午试卷 综合知识
  第75题      
  知识点:   DM
  章/节:   专业英语       

 
Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called(75).
 
 
  A.  Finish-to-Finish
 
  B.  Finish-to-Start
 
  C.  Start-to-Finish
 
  D.  Start-to-Start
 
 
 

  相关试题:专业英语          更多>  
 
  第73题    2022年上半年  
   68%
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , (), opera..
  第73题    2010年下半年  
   53%
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).
  第74题    2012年下半年  
   66%
Stakeholder management refers to managing communications to satisfy needs of, and resolve issues with,project stakeholde..
   知识点讲解    
   · DM
 
       DM
        DM(Delta Modulation)即增量调制,又称ΔM调制,是最简单的有损预测编码方法,早期在数字电话中被采用,是一种最简单的差值脉冲编码。实际的采样信号与预测的采样信号的差的极性若为正,则用1表示,反之则用0表示。由于DM编码只用1位对声音信号进行编码,所以DM系统又称1位系统。
   题号导航      2025年上半年 信息系统项目管理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第75题    在手机中做本题