The uncertainty of an event is measured by its probability of occurrence and is inversely proportional to that. The more uncertain an event is. The more information is required to resolve uncertainty of that event. The amount of information is measured in (73).
 
 
  A.  possibility
 
  B.  bits
 
  C.  bps
 
  D.  probability
 
 
 

  相关试题:专业英语          更多>  
 
  第71题    2009年下半年  
   56%
The (71) process ascertains which risks have the potential of affecting the project and documenting the risks' character..
  第71题    2015年下半年  
   43%
In an Information system. The(71)is the bridge between hardware and people。
  第74题    2019年上半年  
   50%
Earned value management(EVM) integrates the scope baseline with the ( ) baseline, along with schedule baseline,to form t..
   题号导航      2013年下半年 信息系统项目管理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第73题    在手机中做本题