A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in  the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.
 
 
  A.  plan
 
  B.  fraction
 
  C.  main
 
  D.  framework
 
 
 

  相关试题:专业英语          更多>  
 
  第74题    2016年下半年  
   71%
In order to facilitate configuration and change management, manual or automated tools may be used. Tool'selection should..
  第72题    2021年上半年  
   87%
( )is not used on perception layer of Internet of Things.
  第71题    2022年上半年  
   89%
A grid for mpping the probability of occurrence of each impact on project objectives if that risk occurs is used in ()..
   题号导航      2009年上半年 系统集成项目管理工程师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第74题    在手机中做本题