免费智能真题库 > 历年试卷 > 系统集成项目管理工程师 > 2018年下半年 系统集成项目管理工程师 上午试卷 综合知识
  第75题      
  章/节:   专业英语       

 
In a project plan, when the project manager schedules activities, he (or she) often uses ( ) method,This method, precedence relationships between activities are represented by circles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity.
 
 
  A.  causality diagram
 
  B.  Gantt chart
 
  C.  histogram
 
  D.  arrow diagram
 
 
 

  相关试题:专业英语          更多>  
 
  第71题    2015年下半年  
   69%
Software engineering is the study and an application of engineering to the design,development,and (71) of software.
  第74题    2017年上半年  
   63%
( )is a project management technique for measuring project performance progress.It has the ability to combine measuremen..
  第72题    2020年下半年  
   76%
( )is called the gateway of network security, which is used toidentify what kind of data packets can enter the enterp..
   题号导航      2018年下半年 系统集成项目管理工程师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第75题    在手机中做本题