免费智能真题库 > 历年试卷 > 系统集成项目管理工程师 > 2012年下半年 系统集成项目管理工程师 上午试卷 综合知识
  第74题      
  章/节:   专业英语       

 
The project budget has been finalized.Additional work has been discovered that was not planned forin the budget or project scope. (74) could provide the fund to cover the newly discovered work item.
 
 
  A.  Contingency reserve
 
  B.  Project profit
 
  C.  Managementreserve
 
  D.  Special fund
 
 
 

  相关试题:专业英语          更多>  
 
  第73题    2013年下半年  
   76%
(73) is not the advantage of GERT(graphical evaluation and review techniques) as compared with PERT(project evaluation a..
  第72题    2011年下半年  
   60%
A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major imp..
  第72题    2010年下半年  
   60%
Most of the host operating system provides a way for a system administrator tomanually configure the IP information need..
   题号导航      2012年下半年 系统集成项目管理工程师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第74题    在手机中做本题