免费智能真题库
>
历年试卷
>
信息系统监理师
>
2013年下半年 信息系统监理师 上午试卷 综合知识
第75题
关键词:
SOW
章/节:
专业英语
With a clear SOW a contractor completes work as specified, but the buyer is not pleased with the result. The contract is considered to be (75) .
A. incomplete because the buyer is not pleased
B. incomplete because the specs are incorrect
C. complete because the contractor meets the terms and conditions of the contract
D. complete because the contractor is satisfied
本题目为专供试卷题目。
【如需要,请开通】
您暂时无法使用本功能。
【如需要,请开通】
为保障您的权益,请登录
相关试题:
专业英语
更多>
第74题
2023年上半年
0%
Schedule control is concerned with all the followings except (74) .
第71题
2014年下半年
44%
Most of the host operating system provides a way to automated configure the IP information needed by a host Automated co..
第75题
2019年下半年
47%
( )are also known as tally sheets are used to organize facts in a manner that will facilitate the effective collection..
题号导航
2013年下半年 信息系统监理师 上午试卷 综合知识
本试卷我的完整做题情况
1
/
2
/
3
/
4
/
5
/
6
/
7
/
8
/
9
/
10
/
11
/
12
/
13
/
14
/
15
/
16
/
17
/
18
/
19
/
20
/
21
/
22
/
23
/
24
/
25
/
26
/
27
/
28
/
29
/
30
/
31
/
32
/
33
/
34
/
35
/
36
/
37
/
38
/
39
/
40
/
41
/
42
/
43
/
44
/
45
/
46
/
47
/
48
/
49
/
50
/
51
/
52
/
53
/
54
/
55
/
56
/
57
/
58
/
59
/
60
/
61
/
62
/
63
/
64
/
65
/
66
/
67
/
68
/
69
/
70
/
71
/
72
/
73
/
74
/
75
/
第75题 在手机中做本题