A formally chartered group responsible for reviewing,evaluating,
approving,delayingor rejecting changes to the project,and for recording and communication such decisions. It is the ().
 
 
  A.  Change Control System
 
  B.  Change Control Board
 
  C.  Change Control Tool
 
  D.  Change Management Plan
 
 
 

  相关试题:专业英语          更多>  
 
  第74题    2019年下半年  
   64%
When required,the Perform Integrated Change Control process includes a ( ),Which is a formally chartered group respons..
  第73题    2018年下半年  
   67%
The organization shall undertake change in a planned and systematic manner, taking account of the review of the potentia..
  第72题    2017年下半年  
   69%
System and application access control is to prevent( )access to systems and applications.Access to information and app..
   题号导航      2021年上半年 信息系统监理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第73题    在手机中做本题