Project schedule management is made up of six management processes including:activity definition, activity sequencing, (71) , and schedule control by order.
 
 
  A.  activity duration estimating, schedule developing, activity resource estimating
 
  B.  activity resource estimating, activity duration estimating, schedule development
 
  C.  schedule developing, activity resource estimating, activity duration estimating
 
  D.  activity resource estimating, schedule developing, activity duration estimating
 
 
 

 
  第72题    2018年上半年  
   42%
()is a decentralized, distributed and public digital ledger that is used to record transactions across many computers ..
  第71题    2015年下半年  
   43%
In an Information system. The(71)is the bridge between hardware and people。
  第72题    2022年下半年  
   48%
()can be described by the following characteristics: volume, variety,velocity,veracity and value.?
   题号导航      2010年下半年 信息系统项目管理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第71题    在手机中做本题