Project schedule management is made up of six management processes including:activity definition, activity sequencing, (71) , and schedule control by order.
 
 
  A.  activity duration estimating, schedule developing, activity resource estimating
 
  B.  activity resource estimating, activity duration estimating, schedule development
 
  C.  schedule developing, activity resource estimating, activity duration estimating
 
  D.  activity resource estimating, schedule developing, activity duration estimating
 
 
 

  相关试题:专业英语          更多>  
 
  第75题    2017年上半年  
   64%
()seeks to build confidence that a future output or an unfinished output, will be completed in a manner that meets the..
  第72题    2008年上半年  
   59%
The (71) is a eneral description of the architecture of a workflow mana ement system used by the WFMC, in which the ma..
  第73题    2008年下半年  
   63%
The Estimate Activity Resource process is closely coordinated with the (73)process.
   题号导航      2010年下半年 信息系统项目管理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第71题    在手机中做本题