2010年下半年 上午试卷 综合知识
第 71 题
章/节 专业英语  
 
 
Project schedule management is made up of six management processes including:activity definition, activity sequencing, (71) , and schedule control by order.
 
  A.  activity duration estimating, schedule developing, activity resource estimating
 
  B.  activity resource estimating, activity duration estimating, schedule development
 
  C.  schedule developing, activity resource estimating, activity duration estimating
 
  D.  activity resource estimating, schedule developing, activity duration estimating




 
 
相关试题     专业英语 

  第75题    2022年下半年  
Project()management includes the processes required to identify the people, groups or organizations that could impact or be impacted by the project,..

  第75题    2017年下半年  
In project network diagram,the number of critical path is().

  第71题    2011年下半年  
Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools,which involves company actual or ..




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2026 All Rights Reserved
软考在线版权所有