Many useful tools techniques are used in developing schedule. (73) is a schedule network analysis technique that modifies the project schedule to account for limited resource.
 
  A.  Resource leveling
 
  B.  Critical chain method
 
  C.  Schedule compression
 
  D.  PERT




 
 
相关试题     专业英语 

  第72题    2012年上半年  
Models drawn by the system analysts during the process of the structured analysis are (72)。

  第74题    2012年下半年  
Quality management (74).

  第74题    2011年上半年  
You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent Y260..