In all projects,needs must be tempered by schedule ,cost and resource constraints. Project success depends primarily on (74).
 
  A.  Customer satisfactions
 
  B.  Customer compromises in defining its needs
 
  C.  The quality of the schedule and cost control analysis
 
  D.  Exceeding customer requirements through gold-plating




 
 