Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called(75).
 
 
  A.  Finish-to-Start
 
  B.  Finish-to-Finish
 
  C.  Start-to-Start
 
  D.  Start-to-Finish
 
 
 

  相关试题:专业英语          更多>  
 
  第75题    2010年上半年  
   66%
Fair and(73)competition in government procurement around the world is good business and good public policy. Competitiv..
  第74题    2015年下半年  
   50%
Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imp..
  第74题    2018年下半年  
   51%
The (73) process differs from the (74) process in that the former is primarily concerned with acceptance of the delivera..
   知识点讲解    
   · DM
 
       DM
        DM(Delta Modulation)即增量调制,又称ΔM调制,是最简单的有损预测编码方法,早期在数字电话中被采用,是一种最简单的差值脉冲编码。实际的采样信号与预测的采样信号的差的极性若为正,则用1表示,反之则用0表示。由于DM编码只用1位对声音信号进行编码,所以DM系统又称1位系统。
   题号导航      2011年上半年 信息系统项目管理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第75题    在手机中做本题