uring the systems planning phase, a systems analyst conducts a (71)activity to study the systems request and recommend specific action. After obtaining an authorization to proceed, the analyst interacts with (72) to gather facts about the problem or opportunity, project scope and constraints, project benefits, and estimated development time and costs. In many cases, the systems request does not reveal the underlying problem, but only a symptom. A popular technique for investigating causes and effects is called (73)The analyst has analyzed the problem or opportunity, defined the project scope and constraints, and performed (74)to evaluate project usability, costs, benefits, and time constraints. The end product of the activity is (75). The main content must include an estimate of time, staffing requirements, costs, benefits, and expected results for the next phase of the SDLC.
 
 
  A.  system proposal
 
  B.  feasibility analysis
 
  C.  fact-finding
 
  D.  requirement analysis
 
 
 

  相关试题:专业英语          更多>  
 
  第71题    2013年上半年  
   69%
Feasibility should be measured throughout the life cycle of system development. The scope and complexity of an apparentl..
  第74题    2021年上半年  
   60%
The objective of the systems analysis phase is to understand the proposed project, ensure that it will support business ..
  第75题    2019年上半年  
   75%
uring the systems planning phase, a systems analyst conducts a (71)activity to study the systems request and recommend..
   题号导航      2024年上半年 系统分析师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第74题    在手机中做本题