  第74题      
  章/节:   专业英语       

 
You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent Y260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent Y300,000 by this point. Based on these circumstances, your project could be best described as (74).
 
 
  A.  ahead of schedule
 
  B.  behind schedule
 
  C.  on schedule
 
  D.  having not enough information provided
 
 
 

  相关试题:专业英语          更多>  
 
  第74题    2013年上半年  
   67%
Quality control is normally performed by the (74) .
  第72题    2015年上半年  
   56%
Both TCP and UDP belong to (72) layer of the OSI mode。
  第74题    2022年下半年  
   0%
Maintenance activities do not include (74).
   题号导航      2011年上半年 信息系统监理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第74题    在手机中做本题