全部科目 > 信息系统监理师 >
2013年下半年 上午试卷 综合知识
第 71 题
章/节 专业英语  
 
 
Since risk is associated with most projects, the best course of action is to (71)
 
  A.  cover all project risks by buying appropriate insurance
 
  B.  ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner
 
  C.  avoid projects with clear and present risk
 
  D.  identify various risks and implement actions to mitigate their potential impact




 
 
相关试题     专业英语 

  第72题    2017年上半年  
( )is used to model aggregates of information and the relationships these aggregates have to other.

  第73题    2021年上半年  
A formally chartered group responsible for reviewing,evaluating,
approving,delayingor rejecting changes to the project,and for recording and co..

  第73题    2015年上半年  
(73)is the budgeted amount for the work actually completed on the schedule acticity or WBS comonent during a given period。