PDCA (Deming cycle) is an iterative four -step management method used in continual improvement of processes and products. During the ( ) phase,the data and results gathered from the do phase are evaluated. Data is compared to the expected outcomes to see any similarities and differences.
 
 
  A.  plan
 
  B.  act
 
  C.  check
 
  D.  do
 
 
 

  相关试题:专业英语          更多>  
 
  第74题    2024年下半年  
   0%
The (74) is the primary point of contact for users when there is a service disruption, for Service Requests, or even for..
  第71题    2020年下半年  
   47%
The main steps of IT strategic planning do not include (71)。
  第71题    2017年下半年  
   51%
Typically, an IP address refers to an individual host on a particular network. IP also accommodates addresses that refer..
   题号导航      2025年下半年 系统规划与管理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第75题    在手机中做本题